1. Choose a location for the culvert bridge and mark off the area. 2. Dig a trench where the bridge will be placed and make sure it is at least two feet deep. 3. Place culverts in the trench and connect them using concrete or steel. 4. Install footings and abutments, filling the bottom of the trenchRead more
1. Choose a location for the culvert bridge and mark off the area.
See less2. Dig a trench where the bridge will be placed and make sure it is at least two feet deep.
3. Place culverts in the trench and connect them using concrete or steel.
4. Install footings and abutments, filling the bottom of the trench to the level of the footings with gravel.
5. Lay forms for the deck of the bridge and pour reinforced concrete into them.
6. Construct guard rails along the bridge for safety.
7. Install drainage systems, such as pipes and culverts, in the bridge foundation.
8. Backfill any remaining space in the trench with soil.
9. Install marker signs, guard rails, and other necessary equipment.