Direct cost refers to the expense of a specific price of the object from which the company connects easily, its relation with time is that Project direct cost = Summation of the direct cost of individual activities For Increasing duration and decreasing duration Project indirect cost = Daily indirecRead more
Direct cost refers to the expense of a specific price of the object from which the company connects easily, its relation with time is that
Project direct cost = Summation of the direct cost of individual activities
For Increasing duration and decreasing duration
Project indirect cost = Daily indirect cost * Project duration.