Options
- On all the activities
- On all the activities lying on the critical path
- Only on activities lying on the original critical path and having flatter cost slopes
- On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope.
In time-cost optimization of a project, crashing is done on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope. Answer: Option D
In time-cost optimization of a project, crashing is done on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope.
Answer: Option D