- The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
- The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
- Earliest occurrence time of the event from which the activity arrow’ originates, is called earliest start time of the activity
- All the above
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects
Share
All the above Answer: Option 4
All the above
Answer: Option 4