- Event
- Float
- Duration
- Constraint
The difference between the time avail-to do a job and the time required to do the job, is known as
Share
Get Access to:
Get Access to:
Lost your password? Please enter your email address. You will receive a link and will create a new password via email.
Please briefly explain why you feel this question should be reported.
Please briefly explain why you feel this answer should be reported.
Please briefly explain why you feel this user should be reported.
The difference between the time avail-to do a job and the time required to do the job is known as Float. Answer: Option 2
The difference between the time avail-to do a job and the time required to do the job is known as Float.
Answer: Option 2
See less