Options:
- In order to check up the average depth of excavation, ‘Dead man s’ are left at the mid- widths of borrow pits
- The earthwork calculation in excavation is made from the difference in levels obtained with a level
- The earth work in excavation to form the road embankment includes the formation of correct profile and depositing the soil in layers
- All the above
Correct statement will be: In order to check up the average depth of excavation, 'Dead man s' are left at the mid- widths of borrow pits The earthwork calculation in excavation is made from the difference in levels obtained with a level The earth work in excavation to form the road embankment includRead more
Correct statement will be:
Answer: Option 4
See less