- Event flow scheduling technique
- Critical ratio scheduling
- Slotting technique for scheduling
- Short interval scheduling
The technique for establishing and maintaining priorities among the various jobs of a project, is known
Share
Get Access to:
Get Access to:
Lost your password? Please enter your email address. You will receive a link and will create a new password via email.
Please briefly explain why you feel this question should be reported.
Please briefly explain why you feel this answer should be reported.
Please briefly explain why you feel this user should be reported.
The technique for establishing and maintaining priorities among the various jobs of a project is known as critical ratio scheduling. Answer: Option 2
The technique for establishing and maintaining priorities among the various jobs of a project is known as critical ratio scheduling.
Answer: Option 2