Why C.P.M. method of scheduling is preferred to bar charts? What are limitations of bar chart?
Share
Get Access to:
Get Access to:
Lost your password? Please enter your email address. You will receive a link and will create a new password via email.
Please briefly explain why you feel this question should be reported.
Please briefly explain why you feel this answer should be reported.
Please briefly explain why you feel this user should be reported.
C.P.M. method of scheduling is preferred to bar charts as a complete overview of the whole plan is offered, which makes it easy for the management to follow. The following are the limitations of the bar chart: Progress of work is not shown. It lacks a degree of detail. It is unable to depict the intRead more
C.P.M. method of scheduling is preferred to bar charts as a complete overview of the whole plan is offered, which makes it easy for the management to follow.
The following are the limitations of the bar chart: